Container cut-off times gate-in, SI, VGM and customs
Each export container has several deadlines before the vessel sails. Miss one and the box can be rolled to the next ship.
Typical cut-offs
| Cut-off | What it is |
|---|---|
| Gate-in | The last time the container can enter the terminal |
| Documents (SI) | Shipping instructions to the carrier |
| VGM | Verified gross mass to the line or terminal |
| Customs | Shipping bill and let export order |
Why timing matters
A rolled container waits for the next sailing, costs extra storage and may miss the letter of credit shipment date.
Plan back from the sailing
Add time for the trip to the port, the customs examination, weighing and any holiday. For ICD cargo, the rail or road to the port takes extra days.
Tip
Ask your forwarder for the cut-off list at booking time and confirm again two days before.
Several different cut-offs
A booking has more than one deadline. The gate-in cut-off is the last time a container can be received at the terminal. The document cut-off is the last time for shipping instructions and customs filing. The VGM cut-off is the last time to give the weight declaration. For some cargo, such as reefers and dangerous goods, there is an earlier cut-off.
Each of these is set by the terminal or the line, and they differ between ports and vessels, so always ask for them in writing.
Working back from the sailing
A sample plan for an export: vessel sails on day 10. Gate-in closes on day 7, so the container must be stuffed and ready by day 6. The shipping bill is filed on day 5 and the customs examination, if any, must be done by day 6. The cargo is ready at the factory by day 4. Add a buffer day, since a missed gate-in can mean a week's wait for the next vessel.
When cut-offs change
Lines can advance the cut-off when the vessel is ahead of schedule or the port is congested. Keep in touch with your forwarder in the last days, and do not rely on the first date you were given.
Related guides
Good to know.
Do cut-offs change?
Yes. Lines and terminals can change them if the ship schedule moves.
What is a rolled container?
A container that is left behind and goes on a later ship.
Can I get a late gate-in?
Sometimes, for a fee, if the terminal allows.
What happens if I miss the gate-in cut-off?
The line may refuse the container for that vessel. You will need to move it to the next sailing and may pay extra storage or a rebooking charge.